Pending housing starts per capita in Canadian cities

Trailing 12 months ending June 2026 16 of 16 markets published

What this measures

Units with a building permit issued but not yet started, at the end of the reference period, per 1,000 residents. A secondary indicator of the current pipeline, not a forecast of starts.

Pending starts are a useful secondary view of the current permit backlog. Available history is short and the measured relationship with later starts is weak, so this ranking describes current conditions only — it is not a forecast.

Ranked on this single metric only — no composite score.

Observations

  • Vancouver ranks first at 11.36, ahead of Calgary at 8.81.
  • The highest value is 16.0 times the lowest (Hamilton, 0.71).
  • The median is 3.72. The three most populous markets — Toronto, Montréal and Vancouver — rank 13th, 5th and 1st, so this ranking does not simply follow market size.
  • Pending starts per 1,000 exceed 12-month starts per 1,000 in 1 of 16 markets (Vancouver).

Pending starts per 1,000 residents

Full table

Pending starts per 1,000 residents by market, trailing 12 months ending June 2026, with supporting metrics
RankMarketPending /1,000PendingStarts /1,000Pending change
1Vancouver11.3635,0698.72−5.5%
2Calgary8.8116,17713.25−12.8%
3Québec City8.387,5698.87+57.4%
4Halifax5.883,20610.78−21.4%
5Montréal4.1519,0946.20−20.9%
6Victoria3.911,7429.87−24.6%
7Saskatoon3.781,43110.39+76.7%
8Ottawa–Gatineau3.766,3937.79+20.9%
9Winnipeg3.693,5137.48+7.6%
10Moncton3.3365413.47−25.3%
11Edmonton3.255,50311.32+20.5%
12London2.561,6197.57−19.6%
13Toronto2.3916,9923.76+13.4%
14Regina1.123255.81+45.7%
15Kitchener–Cambridge–Waterloo0.946567.94−44.9%
16Hamilton0.716153.66−65.9%
Pending:
Units with a building permit issued but not yet started, at the end of the reference period.
Starts /1,000:
Housing starts (all dwelling types) over the trailing 12 months divided by the CMA population estimate, per 1,000 residents.
Pending change:
Change in pending starts compared with the same month a year earlier.

Analysis behind the numbers

These articles retain their original data periods; the tables on this page show current figures.

Sources and data period

Figures cover the trailing 12 months ending June 2026, the latest period published for all 16 markets. Source data retrieved through September 12, 2026. This page was built on November 8, 2026; the build date is not the data period. Values not published by the source are shown as “Not published”, never estimated.

Methodology, definitions and limitations

Get the monthly Construction Market Brief

One email when new official data is published: what changed in housing starts, real permit growth, construction prices and market mix across 16 Canadian markets. No forecasts, no spam.

    Construction Market Intelligence

    An independent publication built from official Statistics Canada and CMHC data. Current data: trailing 12 months ending June 2026.

    Contains information licensed under the Open Government Licence – Canada. Not affiliated with or endorsed by Statistics Canada or CMHC.